Client in Power Sector

> M/s. Babcock Wilcox Gama Turkey for 125 MW Co-Generation Habib-ullah Coastal Power Plant Quetta.

M/s. Tapal Energy 130 MW Power Plant.

M/s. Bloom & Voss – 10 MW Power Plant for POF.

M/s. Douche Babcock Werke – Bin Qasim Power Plant Unit # 3, 4 & 5 each 210 MW.

M/s. Gul Ahmed Textiles Mills # 1, 2, 3 & 4 – Captive Power Plants.

M/s. Hawker Siddeley Power Engg. – 18 MW Power Plant at Pasni.

M/s. Marubeni – Bin Qasim Power Plant Unit # 5.

M/s. WAPDA/ Zelins – Guddo Thermal Power Station.

M/s. WAPDA/ Zelins – Kot Addo Thermal Power Station.

M/s. Thatta Power plant Ltd.

M/s. Omni Power Plant Ltd.

M/s. JDW Power Plant Ltd.

M/s. JDW Power Plant Ltd.

Client:

M/s. EFU Insurance

Project:

26.35 MW Co-Generation Power Plant at M/s. JDW Sugar Mills Unit-III Ghotki, Sindh, Pakistan.

PROJECT STATUS:

Completed

PROJECT YEAR:

Year: 2016

Scope of Work:

Overall inspection of plant, equipment and machinery e.g. Medium Pressure Boiler, Steam Turbine, Bagasse Conveying system, Turbo Generator, Water Treatment Plant, Steam & Water Piping, Transformer, Grid Station, Control Systems, Fire Fighting Systems, Fuel Storages etc. in terms of risks associated with it and analysis of results to categorize the Risk factor of the plant.
M/s. Omni Power Plant Ltd.

Client:

M/s. EFU Insurance

Project:

13.2-MW Gas Fired GE Jenbacher Power Plant at M/s. Omni Group Matli

PROJECT STATUS:

Completed

PROJECT YEAR:

Year: 2015

Scope of Work:

Overall inspection of facility as per API & NFPA standard for plant, equipment and machinery in terms of risks associated with it and analysis of results to categorize the plant
M/s. Tapal Energy 130 MW Power Plant.

Client:

M/s. Hanlay & Company Private Limited

Project:

Technical Ascertainment of Cause of Damages To 18V38A Diesel Engine at Tapal Energy, Karachi.

PROJECT STATUS:

Completed

PROJECT YEAR:

Year: 2014

Scope of Work:

Overall inspection of installed equipment in terms of losses, analysis and ascertainment of root causes of losses to verify the claims.
M/s. Thatta Power plant Ltd.

Client:

M/s. National Bank of Pakistan.

Project:

Setting up of 05-MW Waste Heat Recovery Power Plant at M/s. Thatta Power Plant Ltd. comprising of Steam Turbine, Turbo Generator, Boiler, Water Treatment Plant & Storages, Allied facilities including Piping/Pump satiations etc.

Project Cost:

PKR 1.60 Billion

Scope of Work:

Pre-Project Study & Project Monitoring

Client:

M/s. EFU Insurance

Project:

23.5-MW Gas Fired GE Jenbacher Power Plant at M/s. Thatta power Plant Ltd.

Project Cost:

PKR 1.60 Billion

Scope of Work:

Overall inspection of facility as per API & NFPA standard for plant, equipment and machinery in terms of risks associated with it and analysis of results to categorize the plant

M/s. Babcock Wilcox Gama Turkey for 125 MW Co-Generation Habib-ullah Coastal Power Plant Quetta.
M/s. Bloom & Voss – 10 MW Power Plant for POF.
M/s. Douche Babcock Werke – Bin Qasim Power Plant Unit # 3, 4 & 5 each 210 MW.
M/s. Gul Ahmed Textiles Mills # 1, 2, 3 & 4 – Captive Power Plants.
M/s. Hawker Siddeley Power Engg. – 18 MW Power Plant at Pasni.
M/s. Marubeni – Bin Qasim Power Plant Unit # 5.
M/s. WAPDA/ Zelins – Guddo Thermal Power Station.
M/s. WAPDA/ Zelins – Kot Addo Thermal Power Station.