Services

Third Party Inspection

Client:

M/s. Marine International Liquid Terminal.

Project:

Geographical Survey of 02 Acre Land Adjacent to MILT Plant

Project Cost:

PKR 200 Million 

Scope of Work:

Geographical survey and field testing of the 2 acre land

Client:

M/s. Clogate Palmolive Pakistan Ltd

Project:

Inspection of Storage tanks

Project Year:

2022

Scope of Work:

ISOTEC’s scope of work encompassed the following activities for the aforementioned storage tanks:

1. Dye Penetrant Test (DPT)

2. Vacuum Box Test (VBT)

3. Hydro Test

Client:

M/s. National Refinery Ltd.

Project:

Shell & Tube Heat Exchanger, Finned Tube Air Cooler/Pre-heater, Pressure Vessels etc. at different manufacturers in Karachi & Lahore.

Project Cost:

PKR Billion

Scope of Work:

To ensure compliance of manufacturing of Pressure Vessels, Heat Exchangers & Air
Coolers according to mainly AMSE Sec. VIII, TEMA & ANSI standards for more than 03- year. Scope of work includes but not limited to verification of material, stage inspection,
certification of WPS & PQR, NDT including DPT & Radiography, hydro testing and final
inspection of equipment.

Client:

M/s. Babcock, Wilcox Gama Turkey

Project:

110-MW Waste Heat Recovery Power Plant at M/s. Habib-ul-lah Coastal power Plant Quetta.

Project Cost:

PKR Billion

Scope of Work:

To carry out Preparation of Consolidated Bill of Materials on DATA FLEX computer software, Preparation of Stage Inspection Formats, Inspection of locally manufactured parts and machinery, Progress Monitoring, Verification of Invoices etc.

Client:

M/s. Dewan Cement Ltd. Karachi

Project:

06-MW Waste Heat Recovery Power Plant

Project Cost:

PKR Billion

Scope of Work:

To carry out Stage Inspections, Preparation of Fortnightly/ Weekly work Progress
Reports, intimation of delays, Preparation of various inspection check lists during
erection/ installation and commissioning etc.

Client:

M/s. Aisha Steel Mills Ltd. Karachi

Project:

08-Nos. OH Traveling Cranes of capacity 45 tons to 25-Tons with 25-m span

Project Cost:

PKR Billion

Scope of Work:

To carry out Third Party Inspector for Local Manufacturing, Installation, Co-ordination
b/w Client and Contractor, preparation of Stage Inspection Reports for various nature of
works e.g. MTC, Assembly, Welding Procedure, NDT Review, Main Assembly, Painting
etc., Assistance in Trial run & Commissioning of Cranes etc.

Client:

M/s. Llyod’s Pakistan

Project:

Inspection of imported mild Steel pipes for M/s. OGDCL Pakistan

Project Cost:

PKR Billion

Scope of Work:

To carry out Third Party Inspection for Dimensions, conditions of pipes and mechanical and chemical testing as per ASTM & API standards.