Projects In Hand

Client:

M/s. National Bank of Pakistan.

Project:

Technical Due Diligence Report 202,684 Bags per Annum Spinning Plant of M/s. Sadaqat Ltd., Faisalabad

Project Cost:

4.47 Billion

PROJECT STATUS:

In Hand

PROJECT DURATION:

2021-2022

Scope of Work:

Due Diligence includes the reasonableness of project cost, adequateness of the Project design and implementation schedule for the plant, with a view to satisfactorily produce the stated capacity during trial run and commissioning

Client:

M/s. Faysal Bank Limited

Project:

Setting up of 5,000 M. Tons Ethanol Storage & Filling along with ISO Tanks Cleaning, Repair & Maintenance Facility by Marine International Liquid Terminal

Project Cost:

PKR 2.03 Billion

PROJECT STATUS:

In Hand

PROJECT DURATION:

2021-2022

Scope of Work:

The project included but not limited to Technical & Financial Feasibility, project EPCC contract, Project Timeline, market study etc.

Client:

M/s. National Bank of Pakistan

Project:

Setting up of 8,000 TPD 3rd Clinker Production Line along with 12-MW Waste Heat Recovery Power Plant at M/s. Pioneer Cement Ltd. Khushab.

Project Cost:

PKR 20.90 Billion

PROJECT STATUS:

In Hand

PROJECT DURATION:

2018-2021

Scope of Work:

Review and comments on Overall Civil, Mechanical, Electrical / Instrumentation & Process design. Also review of Construction Contracts, Project Master & Detailed Schedule, Project Monitoring, Stage Inspection, Verification of Invoices/ Bills etc.

Client:

M/s. Meezan Bank Limited

Project:

Setting up of 24-MW Coal Fired Power Plant at M/s. Pioneer Cement Ltd. Khushab, including Steam Turbine, Turbo Generator, Boiler, Water Treatment Plant & Storages, Effluent/Sewage Treatment plant, Coal Storages & Conveying System and Allied facilities including Piping/Pump satiations etc.

Project Cost:

PKR 3.74 Billion

PROJECT STATUS:

In Hand

PROJECT DURATION:

2018-2021

Scope of Work:

Review and comments on Overall Civil, Mechanical, Electrical / Instrumentation & Process design. Also review of Construction Contracts, Project Master & Detailed Schedule, Project Monitoring, Stage Inspection, Verification of Invoices/ Bills etc.

Client:

M/s. National Bank of Pakistan

Project:

Construction of Zaver Pearl Continental Hotel Hayatbad-Peshawar.

Project Cost:

PKR 2.28 Billion

PROJECT STATUS:

In Hand

PROJECT DURATION:

2015-2022

Scope of Work:

Review of Construction Contracts, Design of Civil Structures & Architecture including HVAC, Plumbing, Electrical & captive Power Generation with other Allied works along with review of Project Master & Detailed Schedule including Project Monitoring, Phase Inspection and Verification of Invoices/ Bills etc.
Ittehad Metals Limited

Client:

M/s. Habib Bank Limited

Project:

M/s. Ittehad Metals Limited is setting up an in-house facility of Cold Rolling Mill to produce ~300,000 Metric Tons per Annum Cold Rolled Coils (“CRC”) also will able to convert at least 75% CRC capacity to Hot Dipped Galvanized Coils (“HDGC”) at Faisalabad, Punjab, Pakistan.

Project Cost:

9.845 Billion

PROJECT STATUS:

In Hand

PROJECT DURATION:

2022-2024

Scope of Work:

Review and comments on the Technical and Financial viability of the project with detailed comments on Suitability of Plant, Equipment & Machinery, Overall Project Cost Evaluation.

Pioneer Cement Limited

Client:

M/s. National Bank of Pakistan

Project:

Construction of Ancillary Buildings, Land Development and Road Works at M/s. Pioneer Cement Ltd. Line-III Project Khushab.

Project Cost:

PKR 4.48 Billion

PROJECT STATUS:

In Hand

PROJECT YEAR:

Year: 2019-2022

Scope of Work:

Review of Contracts awarded, Construction activities, Project Monitoring, Stage Inspection, Verification of Invoices/ Bills etc. for valuation purpose.

Client:

M/s. National Bank of Pakistan

Project:

Setting up of 8,000 TPD 3rd Clinker Production Line along with 12-MW Waste Heat Recovery Power Plant at M/s. Pioneer Cement Ltd. Khushab.

Project Cost:

PKR 20.90 Billion

PROJECT STATUS:

In Hand

PROJECT YEAR:

Year: 2018-2021

Scope of Work:

Review and comments on Overall Civil, Mechanical, Electrical / Instrumentation & Process design. Also review of Construction Contracts, Project Master & Detailed Schedule, Project Monitoring, Stage Inspection, Verification of Invoices/ Bills etc.

Client:

M/s. Meezan Bank Limited

Project:

Setting up of 24-MW Coal Fired Power Plant at M/s. Pioneer Cement Ltd. Khushab, including Steam Turbine, Turbo Generator, Boiler, Water Treatment Plant & Storages, Effluent/Sewage Treatment plant, Coal Storages & Conveying System and Allied facilities including Piping/Pump satiations etc.

Project Cost:

PKR 3.74 Billion

PROJECT STATUS:

In Hand

PROJECT YEAR:

Year: 2018-2021

Scope of Work:

Review and comments on Overall Civil, Mechanical, Electrical / Instrumentation & Process design. Also review of Construction Contracts, Project Master & Detailed Schedule, Project Monitoring, Stage Inspection, Verification of Invoices/ Bills etc.

Client:

M/s. Pioneer Cement Limited

Project:

Designing of Fly Ash Bin

PROJECT STATUS:

In Hand

PROJECT YEAR:

Year: 2022

Scope of Work:

Steel Structure designing of Fly Ash Bin, 150 Ton Capacity

Flying Cement Ltd.

Client:

M/s. Flying Cement Limited

Project:

Designing of RAW MEAL SILO

ISOTEC ROLE:

Designer

PROJECT STATUS:

In Hand

PROJECT DURATION:

2022

Scope of Work:

Steel Structure designing of RAW MEAL SILO-∅ 20 m

Gharibwal Cement Limited

Client:

M/s. Gharibwal Cement Limited

Project:

Design/Drawings of Civil Works and Steel Structure

ISOTEC Role:

Designer

PROJECT STATUS:

In Hand

PROJECT DURATION:

2022

Scope of Work:

Design/Drawings of Civil Works and Steel Structure for New Line.

Sadaqat Limited

Client:

M/s. National Bank of Pakistan.

Project:

Technical Due Diligence Report 202,684 Bags per Annum Spinning Plant of M/s. Sadaqat Ltd., Faisalabad

Project Cost:

4.47 Billion

PROJECT STATUS:

In Hand

PROJECT YEAR:

Year: 2021-2022

Scope of Work:

Due Diligence includes the reasonableness of project cost, adequateness of the Project design and implementation schedule for the plant, with a view to satisfactorily produce the stated capacity during trial run and commissioning
Marine International Liquid Terminal (MILT by PMS – Marine Group)

Client:

M/s. Faysal Bank Limited

Project:

Setting up of 5,000 M. Tons Ethanol Storage & Filling along with ISO Tanks Cleaning, Repair & Maintenance Facility by Marine International Liquid Terminal

Project Cost:

PKR 2.03 Billion

PROJECT STATUS:

In Hand

PROJECT YEAR:

Year: 2021-2022

Scope of Work:

The project included but not limited to Technical & Financial Feasibility, project EPCC contract, Project Timeline, market study etc.
Zaver Pearl Continental Hotel Hayatbad-Peshawar

Client:

M/s. National Bank of Pakistan

Project:

Construction of Zaver Pearl Continental Hotel Hayatbad-Peshawar.

Project Cost:

PKR 2.28 Billion

PROJECT STATUS:

In Hand

PROJECT YEAR:

Year: 2015-2022

Scope of Work:

Review of Construction Contracts, Design of Civil Structures & Architecture including HVAC, Plumbing, Electrical & captive Power Generation with other Allied works along with review of Project Master & Detailed Schedule including Project Monitoring, Phase Inspection and Verification of Invoices/ Bills etc.
Al-Haj Automotive Private Limited

Client:

M/s. Dubai Islamic Bank Karachi

Project:

Setting up of 12,000-Nos. PROTON SAGA & SUV Cars / Annum production Plant by M/s. ALHAJ FAW Motors Automobile (Pvt.) Ltd. Karachi comprising of Body Shop, Paint Shop with Paint robots, Assembly Line, Testing line etc.

Project Cost:

PKR 1.945 Billion

PROJECT STATUS:

Completed

PROJECT DURATION:

2021-2022

Scope of Work:

Review and comments on the technical and financial viability of the project with detailed comments on suitability of plant, equipment & machinery, overall project cost evaluation.